Ningetsu (person-month) / Ninnichi (person-day)

Both of the following terms are used predominantly in the IT field as units of measurement to estimate an amount of work.

人月 にんげつ ningetsu  (person-month)

A person-month is the amount of work done by one person in one month, often based on the assumption of 20 work days in a month. This unit helps measure or estimate the total length of time required to complete a task or project.

例: 1人のプログラマーが1か月働く場合のコストを「人月単価」と言います。
  The cost of one programmer working for one month is called the “unit cost per person-month”.

 

人日  にんにち ninnichi (person-day)

A person-day is the amount of work done by one person in one day, often based on the assumption of 8 hours of work in a day. This unit helps measure or estimate the number of hours required to complete a task or project.

例: このプロジェクトには10人日かかると考えた方がいいと思います。
  I think we should plan on 10 person-days for this project.